# BAAJA Bill Will Barely Move the Needle on US Grid Scaling

*Permalink: https://kumarletter.com/posts/baaja-bill-will-barely-move-the-needle-on-us-grid-scaling*

*Published: 2026-11-25*

**The TL;DR is that the Bipartisan American Affordability and Jobs Act (BAAJA) primarily streamlines**  **_federal_** environmental reviews, while the actual bottlenecks choking the U.S. grid are regional connection backlogs, supply chain shortages, and local/state permitting rules outside of federal jurisdiction.  

![](https://a.postcard.page/rails/active_storage/blobs/proxy/eyJfcmFpbHMiOnsibWVzc2FnZSI6IkJBaHBBb1hiIiwiZXhwIjpudWxsLCJwdXIiOiJibG9iX2lkIn19--fc2b0734e3bdd2f9c0409f096175f19c8b485ccd/image.png)
  
What the bill actually fast-tracks:

- **Environmental Reviews (NEPA).** Puts a 1-to-2-year clock on federal reviews, lets more projects skip full reviews altogether, and puts the application process onto one digital portal.
- **Lawsuits.** Shrinks the window to sue over a permit from 6 years down to **150 days** , restricts who is allowed to sue, and stops judges from shutting down construction over minor paperwork mistakes.
- **Clean Water Rules.** Stops states from using water permits to block projects over broader climate issues, sets a 9-month review limit for big lines and pipes, and doubles standard permit lengths to 10 years.
- **Wildlife & Historic Sites.** Speeds up Endangered Species Act check-ins, narrows what triggers historic preservation reviews, and puts that same 150-day limit on lawsuits.
- **Grid Upgrades.** Lets utilities upgrade power lines along existing routes without going through federal reviews, and gives [FERC](https://www.ferc.gov/) more power to push through major interstate lines.
- **Nuclear & Federal Lands.** Skips mandatory public hearings for uncontested [NRC](https://www.nrc.gov/) nuclear licenses and speeds up energy leasing on federal land.
- **Locked-in Permits.** Stops federal agencies from pulling the rug out from under a project by revoking permits after they've already been approved.

Worst case scenario is that this bill **accelerates connection of new power plants and data centers onto the grid faster than it can build the high-voltage transmission lines needed to carry that electricity.  
  
Someone could make the argument that BAAJA is great for western states since those are federally owned....hogwash.   
  
BAAJA**  
   streamlines federal land permitting across Western states because the federal government owns ~50% of all land in the West, meaning virtually any major power line, solar farm, or mine there automatically triggers the exact federal environmental laws (like NEPA) that BAAJA overhaul. 
![](https://a.postcard.page/rails/active_storage/blobs/proxy/eyJfcmFpbHMiOnsibWVzc2FnZSI6IkJBaHBBb1RiIiwiZXhwIjpudWxsLCJwdXIiOiJibG9iX2lkIn19--c43899b983b0190de6483c4547edac4ee5c6e2d6/image.png)
   
  
Scaling western state grids with data centers is a bad move because it is fragmented, has terrible water sourcing dynamics, and as well horrific intermittency dynamics.   
  

![](https://a.postcard.page/rails/active_storage/blobs/proxy/eyJfcmFpbHMiOnsibWVzc2FnZSI6IkJBaHBBb2JiIiwiZXhwIjpudWxsLCJwdXIiOiJibG9iX2lkIn19--fec4df0edfe0769b8b78674becbda37dceaef5aa/image.png)
  
Roughly 27% of all utility-scale wind and solar capacity in the United States is concentrated in the Western states—even though the region accounts for less than a quarter of the U.S. population and electricity demand.  
  
**FERC has no jurisdiction over ERCOT's interconnection queues, market rules, or reliability standards**. BAAJA explicitly exempts Texas.   
  
  
  
  
  
  